Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending February 21, 2009

Arbennie WRF

  • Septage Receiving Station
    • Panel wiring continues.
  • UV Channel/Effluent Pump Station
    • Install reuse pumps and miscellaneous metals.
  • Centrifuge and Roll Off Slab
    • Canopy installation continues.
  • Headworks
    • Point and patch concrete.
    • Miscellaneous metals installation continues.
  • Clarifiers
    • Clarifier #1 - Idle.
    • Clarifier #2 - Idle.
  • RAS/WAS Pump Station
    • Install RAS/WAS pumps and piping.
  • Site Civil
    • Install effluent and reuse piping.
    • Install scum piping.
  • Digester
    • Install piping to rotary drum thickener and sludge feed pumps.
  • Aeration Basins 1 & 2
    • Begin miscellaneous metals installation.
  • Maintenance Building
    • Install HVAC equipment.
    • Continue painting.
  • Administration Building
    • Install ceramic tile, HVAC equipment, EIFS, and folding partition.
    • Continue painting.
  • Electrical Building No 1
    • Terminate cable.
    • Install chemical skids.
  • Electrical Building No 2
    • Terminate cable.
    • Install ceiling grid .
  • CDM
    • Weekly Progress Meeting
    • Subcontractor Coordination
  • RIBS

    • OCWS Construction Crews
      • RIBS complete.

    Garniers Re-pump Station

    • Speegle Construction
      • Start-up and testing began this week. Pump Station is currently operational.

    OCWS Collection and Transmissions System Improvements

    • OCWS continues inter connect piping to the Arbennie Pritchett WRF.

    « Previous week's update

    « Return to Weekly Update Index

    © Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
    WEB Site Maintained by The Constantine Group