Weekly Updates
Week ending February 21, 2009
Arbennie WRF
- Septage Receiving Station
- UV Channel/Effluent Pump Station
- Install reuse pumps and miscellaneous metals.
- Centrifuge and Roll Off Slab
- Canopy installation continues.
- Headworks
- Point and patch concrete.
- Miscellaneous metals installation continues.
- Clarifiers
- Clarifier #1 - Idle.
- Clarifier #2 - Idle.
- RAS/WAS Pump Station
- Install RAS/WAS pumps and piping.
- Site Civil
- Install effluent and reuse piping.
- Install scum piping.
- Digester
- Install piping to rotary drum thickener and sludge feed pumps.
- Aeration Basins 1 & 2
- Begin miscellaneous metals installation.
- Maintenance Building
- Install HVAC equipment.
- Continue painting.
- Administration Building
- Install ceramic tile, HVAC equipment, EIFS, and folding partition.
- Continue painting.
- Electrical Building
No 1
- Terminate cable.
- Install chemical skids.
- Electrical Building No 2
- Terminate cable.
- Install ceiling grid .
CDM
- Weekly Progress Meeting
- Subcontractor Coordination
RIBS
Garniers Re-pump Station
- Speegle Construction
- Start-up and testing began this week. Pump Station is currently operational.
OCWS Collection and Transmissions System Improvements
- OCWS continues inter connect piping to the Arbennie Pritchett WRF.