Weekly Updates
Week ending February 28, 2009
Arbennie WRF
- Septage Receiving Station
- UV Channel/Effluent Pump Station
- Install panels and miscellaneous metals.
- Centrifuge and Roll Off Slab
- Canopy installation continues.
- Headworks
- Point and patch concrete.
- Miscellaneous metals installation continues.
- Clarifiers
- Clarifier #1 - Grout Repair Underway.
- Clarifier #2 - Grout Repair Underway.
- RAS/WAS Pump Station
- RAS/WAS pumps and piping is complete. Pouring of the pump slabs continues.
- Site Civil
- Install effluent and reuse piping.
- Install scum piping.
- Digester
- Install piping to rotary drum thickener and sludge feed pumps.
- Aeration Basins 1 & 2
- Walkway and handrail installation continues .
- Maintenance Building
- Install HVAC equipment, ceramic tile, and toilet accessories.
- Paint canopy steel.
- Administration Building
- Install ceramic tile, HVAC equipment, EIFS, toilet accessories and folding partition.
- Continue painting.
- Electrical Building
No 1
- Terminate wire.
- Install chemical skids.
- Electrical Building No 2
CDM
- Weekly Progress Meeting
- Subcontractor Coordination
RIBS
Garniers Re-pump Station
- Speegle Construction
- Pump Station is currently operational.
OCWS Collection and Transmissions System Improvements
- OCWS continues inter connect piping to the Arbennie Pritchett WRF.