Weekly Updates
Week ending April 11, 2009
Arbennie WRF
- UV Channel/Effluent Pump Station
- Centrifuge and Roll Off Slab
- Install piping .
- Rough-in electric.
- Install reuse water lines.
- Headworks
- Complete bar screen and handrail.
- Clarifiers
- RAS/WAS Pump Station
- Install knife gate valves.
- Install walkways.
- Site Civil
- Pipe testing continues.
- Install walkways.
- Digester
- Install piping to rotary drum thickener, centrifuge, and sludge feed pumps.
- Aeration Basins 1 & 2
- Walkway and handrail installation continues.
- Electrical installation continues.
- Fill basins for hydrostatic testing.
- Maintenance Building
- Install floor tile and ceiling tile.
- Administration Building
- MEP trimout.
- Install floor tile.
- Install computer equipment .
- Electrical Building
No 1
- Electrical Building No 2
CDM
- Weekly Progress Meeting
- Subcontractor Coordination
RIBS
Garniers Re-pump Station
- Speegle Construction
- Pump Station is currently operational .
OCWS Collection and Transmissions System Improvements
- OCWS continues inter connect piping to the Arbennie Pritchett WRF.