Arbennie WRF

  • UV Channel/Effluent Pump Station
    • Complete handrail .
  • Centrifuge and Roll Off Slab
    • Install piping .
    • Rough-in electric.
    • Install reuse water lines.
  • Headworks
    • Complete bar screen and handrail.
  • Clarifiers
    • Idle.
  • RAS/WAS Pump Station
    • Install knife gate valves.
    • Install walkways.
  • Site Civil
    • Pipe testing continues.
    • Install walkways.
  • Digester
    • Install piping to rotary drum thickener, centrifuge, and sludge feed pumps.
  • Aeration Basins 1 & 2
    • Walkway and handrail installation continues.
    • Electrical installation continues.
    • Fill basins for hydrostatic testing.
  • Maintenance Building
    • Install floor tile and ceiling tile.
  • Administration Building
    • MEP trimout.
    • Install floor tile.
    • Install computer equipment .
  • Electrical Building No 1
    • Terminate wire.
  • Electrical Building No 2
    • Terminate wire.
  • CDM
    • Weekly Progress Meeting
    • Subcontractor Coordination
  • RIBS

    • OCWS Construction Crews
      • RIBS complete.

    Garniers Re-pump Station

    • Speegle Construction
      • Pump Station is currently operational .

    OCWS Collection and Transmissions System Improvements

    • OCWS continues inter connect piping to the Arbennie Pritchett WRF.