Weekly Updates
Week ending April 25, 2009
Arbennie WRF
- UV Channel/Effluent Pump Station
- Install field instruments and terminate wire.
- Centrifuge and Roll Off Slab
- Completel piping.
- Terminate wire.
- Headworks
- Electrical installation continues.
- Install odor control.
- Biofilter
- Install media and piping.
- Clarifiers
- Install scum collectors.
- Begin hydrostatic testing.
- RAS/WAS Pump Station
- Install knife gate valves and handrail.
- Site Civil
- Pipe testing continues.
- Install walkways.
- Digester
- Install air pipe to diffusers.
- Terminate wire.
- Aeration Basins 1 & 2
- Walkway and handrail installation continues.
- Electrical installation continues.
- Maintenance Building
- Install signage.
- Form and pour sidewalks.
- Administration Building
- Install signage.
- Install computer equipment.
- Form and pour sidewalks.
- Electrical Building
No 1
- Electrical Building No 2
CDM
- Weekly Progress Meeting
- Subcontractor Coordination
RIBS
Garniers Re-pump Station
- Speegle Construction
- Pump Station is currently operational .
OCWS Collection and Transmissions System Improvements
- OCWS inter connect piping to the Arbennie Pritchett WRF is complete.