Week ending May 2, 2009
Arbennie WRF
- UV Channel/Effluent Pump Station
- Complete handrail.
- Install reuse water line.
- Centrifuge and Roll Off Slab
- Terminate wire.
- Pour topping on roll off slab.
- Headworks
- Electrical installation continues.
- Install odor control.
- Biofilter
- Install media and piping.
- Clarifiers
- Hydrostatic testing underway.
- Complete rake arm installation.
- RAS/WAS Pump Station
- Install knife gate valve operators.
- Begin hydrostatic testing.
- Site Civil
- Pipe testing continues.
- Install walkways.
- Digester
- Install air pipe to diffusers.
- Aeration Basins 1 & 2
- Walkway and handrail installation continues.
- Electrical installation continues.
- Maintenance Building
- Complete floor tile installation.
- Administration Building
- Install signage.
- Install computer equipment.
- Electrical Building
No 1
- Electrical Building No 2
CDM
- Weekly Progress Meeting
- Subcontractor Coordination
RIBS
Garniers Re-pump Station
- Speegle Construction
- Pump Station is currently operational .
OCWS Collection and Transmissions System Improvements
- OCWS inter connect piping to the Arbennie Pritchett WRF is complete.