Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending June 20, 2009

Arbennie WRF

  • UV Channel/Effluent Pump Station
    • Install UV modules.
    • Paint pumps and piping.
    • Checkout effluent and reuse pumps.
    • Install influent flow meter.
  • Centrifuge and Roll Off Slab
    • Idle.
  • Headworks
    • Install aluminum covers at grit chutes.
  • Biofilter
    • Complete
  • Clarifiers
    • Idle.
  • RAS/WAS Pump Station
    • Paint pumps and pipe.
  • Digester
    • Idle.
  • Aeration Basins 1 & 2
    • Fill with RIBs water.
  • Maintenance Building
    • Punch list.
  • Administration Building
    • Punch list.
  • Electrical Building 1&2
    • Seal floors, install signage, and paint.
  • Site Civil
    • Grade and contour site.
  • CDM
    • Weekly Progress Meeting
    • Subcontractor Coordination