Weekly Updates

Week ending August 1, 2009

Arbennie WRF

  • UV Channel/Effluent Pump Station
    • Pump pre-treated effluent to RIBs.
    • Install manhole and pipe for reuse strainer drain.
  • Centrifuge and Roll Off Slab
    • Idle.
  • Headworks
    • Pour dumpster pad at septage receiving.
    • Install grit classifier cyclone vents.
  • Biofilter
    • Complete.
  • Clarifiers
    • Wet checkout.
  • RAS/WAS Pump Station
    • Wet checkout.
  • Digester
    • Install pinch valve support.
  • Aeration Basins 1 & 2
    • Wet checkout.
  • Maintenance Building
    • Complete.
  • Administration Building
    • Complete.
  • Electrical Buildings 1&2
    • Punch list.
  • Site Civil
    • Grade site and roads.
    • Install conduits for site lighting.
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.
    • Startup Activities.
    • Complete Punch List Items and Bulletins.