Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending August 8, 2009

Arbennie WRF

  • UV Channel/Effluent Pump Station
    • Install manhole and pipe for reuse strainer drain.
    • Cut overflow weir in effluent wetwell wall.
    • Install splash guard baffle at effluent channels.
  • Centrifuge and Roll Off Slab
    • Idle.
  • Headworks
    • Install grit classifier cyclone vents.
  • Biofilter
    • Complete.
  • Clarifiers
    • Wet checkout.
  • RAS/WAS Pump Station
    • Install external sludge acceptance fitting at WAS pumps.
    • Install sludge sampling ports at RAS pumps.
  • Digester
    • Install pinch valve support.
  • Aeration Basins 1 & 2
    • Wet checkout.
  • Maintenance Building
    • Complete.
  • Administration Building
    • Complete.
  • Electrical Buildings 1&2
    • Punch list.
  • Site Civil
    • Grade site and roads.
  • CDM
    • Weekly Progress Meeting.
    • Subcontractor Coordination.
    • Startup Activities.
    • Complete Punch List Items and Bulletins.