Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending August 29, 2009

Arbennie WRF

  • UV Channel/Effluent Pump Station
    • Operational.
  • Centrifuge and Roll Off Slab
    • Start up Centrifuge.
  • Headworks
    • Operational.
  • Biofilter
    • Operational.
  • Clarifiers
    • Operational.
  • RAS/WAS Pump Station
    • Operational.
  • Digester
    • Accepting offsite sludge.
    • Start up Rotary Drum Thickener.
  • Aeration Basins 1 & 2
    • Operational.
    • Painting has begun.
  • Maintenance Building
    • Complete.
  • Administration Building
    • Complete.
  • Electrical Buildings 1&2
    • Punch list.
  • Site Civil
    • Grade and contour site and roads.
    • Install main entrance gate.
    • Install light poles.
    • Install fencing.
  • CDM
    • A combination of raw wastewater and mixed liquor were introduced to the plant on 8/11/09.
    • Monthly Progress Meeting.
    • Subcontractor Coordination.
    • Startup Activities.
    • Complete Punch List Items and Bulletins.