Weekly Updates
Week ending September 19, 2009
Arbennie WRF
- UV Channel/Effluent Pump Station
- Operational, channel 2 running in automatic mode.
- Prepare overflow weir splash pad.
- Centrifuge and Roll Off Slab
- Headworks
- Operational.
- Begin painting.
- Biofilter
- Clarifiers
- East Clarifier online.
- Cleaning West Clarifier weirs.
- RAS/WAS Pump Station
- Digester
- Operational.
- Accepting offsite sludge.
- Painting complete.
- Aeration Basins 1 & 2
- Maintenance Building
- Administration Building
- Electrical Buildings 1&2
- Punch list.
- Performance Guarantee testing.
- Site Civil
- Grade and contour site and roads.
- Begin site paving.
- Install sight lighting.
- Install fencing.
- Continue landscaping and irrigation system installation.
- CDM
- A combination of raw wastewater and mixed liquor were introduced to the plant on 8/11/09.
- Daily O&M Coordination Meetings.
- Subcontractor Coordination.
- Startup Activities.
- Complete Punch List Items and Bulletins.