Week ending October 03, 2009
Arbennie WRF
- UV Channel/Effluent Pump Station
- Operational, channel 2 running in automatic mode.
- Cleaning of UV Banks in channel 1.
- Centrifuge and Roll Off Slab
- Operational.
- Begin painting platform.
- Headworks
- Operational.
- Finish painting.
- Biofilter
- Clarifiers
- RAS/WAS Pump Station
- Digester
- Aeration Basins 1 & 2
- Maintenance Building
- Administration Building
- Electrical Buildings 1&2
- Punch list.
- Performance Guarantee testing.
- Site Civil
- Grade and contour site and roads.
- Continue site paving.
- Install sight lighting.
- Fencing complete.
- Continue landscaping and irrigation system installation.
- CDM
- A combination of raw wastewater and mixed liquor were introduced to the plant on 8/11/09.
- Monday, Wednesday, Friday O&M Coordination Meetings.
- Subcontractor Coordination.
- Startup Activities.
- Complete Punch List Items and Bulletins.