Arbennie Pritchett Water Reclamation Facility Arbennie Pritchett Water Reclamation Facility Program, Okaloosa County Water and Sewer Department Okaloosa County and Constantine Engineering
Constantine Engineering Okaloosa County Water & Sewer

Weekly Updates

Week ending October 17, 2009

Arbennie WRF

  • UV Channel/Effluent Pump Station
    • Operational, channel 2 running in automatic mode.
  • Centrifuge and Roll Off Slab
    • Operational.
    • Solids Performance Guarantee Testing.
    • Painting structural steel.
  • Headworks
    • Operational.
  • Biofilter
    • Operational.
  • Clarifiers
    • East Clarifier online.
  • RAS/WAS Pump Station
    • Operational.
  • Digester
    • Operational.
    • Solids Performance Guarantee Testing.
  • Aeration Basins 1 & 2
    • West basin online.
  • Maintenance Building
    • Complete.
  • Administration Building
    • Complete.
  • Electrical Buildings 1&2
    • Punch list.
    • Performance Guarantee testing.
  • Site Civil
    • Site paving complete. Striping of parking lot. Begin additional paving of Roberts Blvd.
    • Sight lighting complete.
    • Fencing complete.
    • Continue landscaping and irrigation system installation.
  • CDM
    • A combination of raw wastewater and mixed liquor were introduced to the plant on 8/11/09.
    • Plant has been in compliance for 64 consecutive days.
    • Monday, Wednesday, Friday O&M Coordination Meetings.
    • Monthly Construction Meeting.
    • Subcontractor Coordination.
    • Startup Activities.
    • Complete Punch List Items and Bulletins.

    « Previous week's update

« Return to Weekly Update Index

© Copyright All Rights Reserved. Privacy Policy | Terms of Use | Site Map |
WEB Site Maintained by The Constantine Group